Texas A&M University logo: TAMU Homepage
MY ACCOUNT

Sign In
Parking
Transit
Special Events
Fleet
Bicycles

Lot & Garage Rehabilitation Projects

Kimley-Horn and Associates, Inc. logo

Kimley-Horn and Associates, Inc. is an engineering firm contracted by Transportation Services to provide the following:

  • Evaluate and prioritize surface parking areas and rank in order of priority for reconstruction or maintenance.
  • Produce preliminary options and probable construction costs of each lot in order to provide a basis for budgeting future construction.
  • Produce construction documents based on initial investigation and soil reports, and create an annual maintenance program to help extend the life of the parking areas.
  • Assess the five parking garages on campus to document the existing general condition of the facility identifying both well performing or deficient items.
  • Generate a plate of the necessary maintenance work for each garage and the probable cost for each garage


Click on Future Projects or a year below for more details.

Questions? Email Clint Willis at

  • Lot 61
    • Dates: Spring 2010 - August 2010
    • Estimated Budget: $1.5 million
    • Summary: Improve drainage and landscaping to include protection of existing oak trees. Improve drive lanes. Replace exisitng parking lot subgrade and surface.
    • Lot 61 before renovation
      Before
  • Lot 100 i,j and 100k
    • Dates: December 2009- Feb 2010
    • Budget: $600,000
    • Summary: These 3 lots will become 1 lot to decrease number of intersections and make 4-way stop. This will improve traffic flow and safety at Chandler and Olsen. Remove exisiting asphalt in 100j and relplace with concrete. Improve ADA compliance in 100j and k.
    • Lot 100j before renovation
      Before
  • Motorcycle Parking on Mosher
    • Dates: May 17 - August 30, 2009
    • Estimated Budget: $20,000
    • Summary: Over 70 motorcycle spaces added to the south side of campus.
    • new motorcycle parking added on Mosher Lane
  • Lot 30a & b
    • Dates: June 13 - August 7, 2009
    • Estimated Budget: $300,000
    • Summary: Lots 30a and b near the Northside Residence Halls have gone through major renovations over the summer. The existing asphalt was removed and then replaced with a mixture of 6" lime, 6" base and then 2" of asphalt. Drainage for the lot was improved and a larger space for the oak tree in lot 30a was provided. This resulted in the removal of one parking space but allowed for better care of the large oak. Additional motorcycle parking spaces are now found in lot 30 as well as disabled spaces and an improved ramp. Recycled tires provide the material for the new wheel stops, which line the new sidewalk along 30b.

      Before
      Lot 30 During constructionlot 30 asphalt is poured 8/03lot 30 diabled ramps added
      During
  • Lot 36a-e
    • Dates: June 11 - September 15, 2009
    • Estimated Budget: $1.5 million
    • Summary: Four sections of this lot have gone through numerous improvements: Expansion joints have been added every 30 feet within the newly poured concrete to allow for expansion when the temperatures reach extremes such as those we have experienced this summer. Control joints are placed every 15 feet which "move" with the concrete and prevent cracks. Lighting has been added throughout the lot and especially lot sections D and E, to assist with safety in the area. As with all lots, drainage is very important and these lots have been carefully engineered by Kimley-Horn and Associates, Inc., to allow for the optimum runoff, which is critical in maintaining the life expectancy of the lot. Lime has been added to the soil prior to the concrete, which allows for better compaction of the soil and therefore provides a more solid base. With 6" of subgrade and another 6" of concrete, these lots should expect at least 30 years of use before any improvements are needed. Dumpster pads have been added throughout lot 36 and customers will now enjoy additional motorcycle parking adjacent to many light poles. The drive lanes have been improved and parking spaces have been enlarged to 9'x18'. Handicapped ramps have also been added. Lot 36 gained 31 spaces.

      Before
      Lot 36 During constructionConcrete is poured 6-29
      During
      Lot 36 ready for customers July 13
      After
  • Lot 1: John Connally Building - Tarrow Drive at Spring Loop
    • Dates: October 3, 2008 - March 15, 2009
    • Estimated Budget: $700,000
    • Summary: The existing pavement in this lot will be refurbished with a mix of asphalt and cement in order to stabilize the surface of the lot. Concrete drainage flumes, slotted drains, and underground piping will be added to aid in water runoff in order to further lessen the wear and tear on the lot.
      Lot 1 before construction
      Before
      Lot 1 during construction
      During
      Lot 1 after construction
      After
  • Lot 83:
    • Summary of improvements: The old asphalt was removed and fly ash added in order to harden the base and eliminate soft spots which can cause potholes. The base is now good and compacted and should benefit from these improvements for at least 10-15 years. The ramp for ADA accessibility was raised near the handicapped spaces. Re-striping was also completed in the lot.
      lot 83 before renovation
      Before
      ADA ramps have been addedlot 83 completed August 2009
      After

1250 TAMU • College Station, TX 77843-1250 • 979.845.9700
Home | Parking | Transit | Special Events | Bicycles | Fleet
Accessibility Policy |  University Privacy and Security Policy |  University Contacts
Glossary | Privacy Policy | Sitemap | FAQs | | Contact Us